China's earliest production and processing of aluminum veneer ceiling, one of the curtain wall manufacturers
All engineering and technical personnel in the 1. must carefully digest and absorb the blueprint of curtain wall construction design, organize all aspects to conduct joint review of drawings, strengthen the understanding of drawings, solve contradictions and problems existing in drawings and change materials, etc., and make joint review records of drawings and relevant meeting records.
2. in strict accordance with the construction drawings,aluminum honeycomb panelAccording to the blueprint of curtain wall design and construction, engineering and technical personnel shall carry out construction sample design for embedded parts, aluminum plate plate and glass plate making, etc. and prepare construction technology. The construction team must strictly follow the drawing and construction according to the process regulations.
3. strictly control design changes and material substitution, all engineering design changes and material substitution, must be approved by the owner and design unit.
The 4. shall earnestly do a good job of technical disclosure. The main technical problems shall be organized and recorded by the on-site technical director before construction, and signed by both parties. Before the construction of each sub-project, the builder, I .e. the construction team leader, shall organize the technical disclosure to the team in terms of quality requirements, process regulations and safe production, etc., and implement the team layer-by-layer disclosure method to control the whole process.
The 5. has set up a special field measurement team, and the elevation and coordinates and the main axis network are uniformly measured and marked by the measurement team.
6.hollow carved plateStrengthen quality supervision and management, set up a quality supervision team on site, allocate full-time quality inspectors and teams to set up self-inspectors. At the same time of carrying out full-time inspection, carry out self-inspection and mutual inspection and process handover inspection for teams and groups to form a network.
7. special attention should be paid to strengthening the technical review and acceptance of concealed works.
After the installation of the cross material of the 8. stile,arc honeycomb panelShould do a good job in the middle of the acceptance, fire isolation layer before sealing should do a good job of concealed works acceptance, the completion of the whole project should be self-inspection, self-inspection after qualified by the supervision owner acceptance finally reported to the quality supervision station for acceptance.